and referenced in daily inspection reports. c. Form DC-29 (or DC-144 or approved equal) is used for daily inspection reports and the instruction on the DC-29 are followed. DC’s are supplemented with field notes, pay quantity summaries and photographs that tie the work being done to the plans, specifications and related contract documents (http://www.state.ni.us/transportation/business/localaid/documents/DC29 d. Inspection reports are signed and dated by the inspectors. e. The Resident Engineer reviews and initials the daily inspection reports. f. The Resident Engineer prepares a summary of pay quantities based on the daily inspection reports g. The Resident Engineer uses the summary of pay items to develop periodic pay Procedure for Administration and Inspection of Federal Aid Highway Projects Page 28
estimates for the RC/PM. The summary of pay items must be used for comparison and negotiations of Contractor payment request. The RC/PM must ensure proper payments are being made in accordance with the contract provisions. Upon acceptance of the negotiated Contractor payment, a voucher request will be forwarded to Township of West Orange Chief Financial Officer for Contractor payment. h. The Resident Engineer reviews prevailing wage rate requirements of 23 U.S.C and the Davis-Bacon Act, and documents in the Township of West Orange’s project files. i. NEPA and all environmental commitments and/or permit requirements must be met and documented in the daily inspection reports. j. All pedestrian facilities must be constructed or reconstructed in accordance with the American with Disabilities Act (ADA) of 1990; Section 504 of the Rehabilitation Act of 1973; 28 CFR Part 35.151 (e) and NJDOT Standard Construction Details. k. DBE requirements are monitored and enforced to ensure compliance with 49 CFR 26; the contract plans, specifications and related contract documents; the NJDOT Construction Handbook Section V, Subsection B and NJDOT DBE/ESBE Programs. 6.6 Buy America Steel or iron products including application of coating permanently incorporated into federal-aid projects must be manufactured in the United States as per Title 23 CFR 635.410 requirements. These requirements apply to the entire federal-aid project. There is no exemption for steel and iron purchased with other than federal funds. Minimal use of foreign steel or iron is permissible if the cost of such materials does not exceed one-tenth of one percent of the total cost or $2,500, whichever is greater. Pursuant Section 3 of this document, the RC/PM, as responsible charge, will request to the Resident Engineer and Inspector to ensure that the Buy America Certification be provided at the time of material delivery. No steel or iron will be incorporated into the project without a signed Buy America certification. The certification must be properly labeled as per project specific, and be current, dated, signed and notarized, and specific to the
orated into the project without a signed Buy America certification. The certification must be properly labeled as per project specific, and be current, dated, signed and notarized, and specific to the materials at hand and should be delivered prior to steel/iron material is installed. The certification must be printed on the supplier letterhead. This will be documented in the daily inspection reports. The Resident Engineer will maintain a log of all the steel placed on the project; permanently incorporated, temporary, and temporary but must remain in place (stay in place forms, temporary sheeting left in place by the Contractor). 6.7 DBE/Trainee Compliance A specified DBE goal is received from NJDOT-Local Aid by the Township of West Orange and included on the Federal Attachments of the bid documents. The RC/PM and the Resident Engineer continuously monitor DBE and Trainee participation and perform Commercial Useful Function reviews as the project progresses and are responsible for ensuring the DBE contract goals will be Procedure for Administration and Inspection of Federal Aid Highway Projects Page 29
met at the time of project completion. Under the supervision of the RC/PM, the Resident Engineer is responsible and maintains a separate file for: a. Verification of Recommendation to Award memorandum and the schedule of Participation DBE Form CR-266, to determine status of Sub-contractors to monitor for compliance. b. During the course of the Contract, monitors true participation by comparing DBE goal commitments against Request for Approval to Submit Form DC-18; also, cross check the daily reports with each affected Form DC-18, the Recommendation to Award and the Utilization of DBE/SBE Monthly Report Form CR-267. c. Ensure all DBEs are performing Commercial Useful Function (CUF) Reviews. d. Uses the Daily Work Report to document on-site monitoring of stipulated DBE work items and Contractor performing the work under to ensure compliance. e. Notifies the RC/PM and the Contractor in writing of any violations and will direct the Contractor to comply with the requirements. Revisions to the approved DBE program can be made only upon the Contractor submittal of the revised Form CR-266F. The resident Engineer must follow-up promptly to ensure timely solution. f. For any DBE/ESBE goal commitments, outlined in the Specifications, which are not fulfilled, the contactor must promptly submit supporting adequate Good Faith Effort with Form CR-268, this will be reviewed by RC/PM and recommended documentation for approval and sent to NJDOT-Local Aid Office. Changes to DBE compliance must be approved by NJDOT Office of Civil Rights. g. Executed sub contracts h. DC-18’s, cancelled checks showing payment to sub-contractors – copies of front and back of check to be provided i. DC 18s must be provided to NJDOT Local Aid before subcontractors begin work. j. RC/PM monitors Trainee goal Requirements (If Trainees are Required) through on-site monitoring (DC-29A Daily Inspector’s
ubcontractors begin work. j. RC/PM monitors Trainee goal Requirements (If Trainees are Required) through on-site monitoring (DC-29A Daily Inspector’s Report/or DC-144 or Local Form will be used to monitor the performance of the Trainees). Evidence of Contractor’s Trainee compliance must be maintained throughout contract. k. Township will have Contractor provide and maintain Apprentice/Trainee Approval Memorandum Part "A", Biweekly Training Reports, Contractor's 1409 Quarterly Training Reports, and Training Certificate for each Trainee candidate assigned to project. 6.8 Contract Changes, Project Schedule, Contract Completion Contract Changes/Change Orders Changes in the plans and specifications, and extra work (if necessary) are to be done in accordance with the requirements of NJDOT Standard Specifications, Section 104.03 and Title 23 CFR 635.120 and the procedure outlined below. Procedure for Administration and Inspection of Federal Aid Highway Projects Page 30
Contract changes must be monitored and documented daily. The Contractor may not deviate from the requirements of the contract unless and until a field order is issued by Resident Engineer upon approval by the RC/PM and NJDOT Local Aid. Contract line item overruns are not permissible without formal requests by the Contractor and approvals by the RC/PM. All new or supplemental costs must be negotiated, itemized and justified. All documentation of the negotiations, including the basis of cost, must be on file and included in the change order request. The Resident Engineer will notify the RC/PM once it becomes apparent that a change to the Plans and/or Specifications is required. After reviewing the plans and/or Specifications to determine if the change is valid and necessary in conjunction with the consultant who designed the project the potential extra work is evaluated and recommended for approval. The RC/PM notifies the NJDOT- Local Aid Office once it has been established that a Change Order for changes in the contract quantity or extra work/new work is necessary and prepares a field order. The form shall state the description of the change or extra work (new work), reason for the change, value of the change (increases or decreases against the contract price). Time is also evaluated as part of the change order. This form will authorize the Contractor to proceed with the work upon written approval from NJDOT Local Aid. The Contractor should provide to the Resident Engineer a detailed cost proposal (materials, labor, equipment, overhead) for extra (new work). The cost will be reviewed by the Resident Engineer and the RC/PM, documented, and negotiated based on the cost estimate prepared by the Resident Engineer, under the supervision and approval of the RC/PM, for the extra work cost presented by the Contractor. The negotiated costs will be included in the change order. The change order will be signed by the Contractor, the Resident Engineer and submitted to the RC/PM for review. If the price for extra/new work cannot be mutually agreed upon, the Township of West Orange will initiate work by force account as per Section 104.03 of the Standard Specifications. The RC/PM prepares a Federal Aid Change Order (DC-173A) and submits it to NJDOT for their review and approval once the Municipal Council approves the change order. The Change Order will serve as a
s. The RC/PM prepares a Federal Aid Change Order (DC-173A) and submits it to NJDOT for their review and approval once the Municipal Council approves the change order. The Change Order will serve as a contract document adjusting the contract price. Any amounts in excess of the authorized contract amount cannot be expended until the Change Order is approved. Time should always be evaluated as part of a change order, because it will change the contract time and contract completion date, therefore any change order must include the required additional time for extra work. The RC/PM will notify NJDOT if during the course of construction, an inherent job condition should arise, and said condition, if not immediately corrected or changed, would unduly delay the Contractor. Upon the written authorization of the NJDOT, the Contractor will be instructed by field order and the Township of West Orange will proceed with the approval of the change order at the next available Municipal Council meeting. 6.9 Field Orders (Appendix E) The RC/PM will notify NJDOT Local Aid, if during the course of construction, an inherent job condition should arise, and said condition, if not immediately corrected or changed, would unduly delay the project completion. The Contractor will provide to the Resident Engineer and RC/PM Procedure for Administration and Inspection of Federal Aid Highway Projects Page 31
a detailed cost proposal (materials, labor, equipment, overhead) for extra (new work). The negotiated cost will be sent to NJDOT Local Aid and included in the Change Order (Form DC- 173A). Upon approval by NJDOT Local Aid, the Contractor will be instructed by Field Order to proceed with the work. The process for a Field Order shall be as follows: a. The contractor shall immediately notify the Resident Engineering that there is a need for a Field Order. b. The Resident Engineer shall set up a meeting in the field to include the Contractor and the RC/PM to discuss the needed change, potential cost impacts and potential changes to the Progress Schedule. c. Once the change has been agreed upon by all parties, the Resident Engineer shall issue, after the meeting, a written description of the change, including the immediate need for the change and the anticipated cost. d. The RC/PM will evaluate the Field Order request and, if acceptable, immediately notify the NJDOT Local Aid by e-mail. Upon written approval from NJDOT Local Aid, the Resident Engineer shall then issue a verbal approval to the contractor. The contractor can then proceed with the Field Order. The Resident Engineer will immediately prepare a written approval of the Field Order after verbal approval is given. The Resident Engineer shall record and verify all work and quantities related to the Field Order and immediately notify the RC/PM if the estimated work for the change should differ significantly f rom what was discussed. If there are significant differences, RC/PM shall decide whether a revised field change order is required. e. The RC/PM will proceed with the approval of the Field Order at the next available Municipal Council meeting and submit to NJDOT Local Aid for formal approval by use of a Federal Aid Change Order (Form DC-173A) as outlined above. 7.0 Contract Completion Date Contract Completion – Time of Completion and Liquidated Damages shall be in accordance with NJDOT Standard Specification, Section 108.10. The RC/PM issues a formal “Notice-To- Proceed” (NTP), once all Civil Rights documents have been submitted and approved by the NJDOT and all Pre-Construction Meeting Checklist items are completed. The NTP
RC/PM issues a formal “Notice-To- Proceed” (NTP), once all Civil Rights documents have been submitted and approved by the NJDOT and all Pre-Construction Meeting Checklist items are completed. The NTP must include the Contract Completion Date. The Resident Engineer with the supervision of RC/PM, schedules progress review meeting periodically to evaluate the progress on the project and request progress schedule updates from the Contractor. If the Contractor falls behind the schedule, the Contractor will be notified in writing and asked to make every effort to improve the progress. The Contractor will be advised by the Resident Engineer, who will ensure that, contract time extensions will only be granted for excusable delays specified in Section 108.11 of the NJDOT Procedure for Administration and Inspection of Federal Aid Highway Projects Page 32
2019 Standard Specifications and shall be submitted and approved by Change Order as the project progresses and at the time an excusable delay occurs. If the Contractor fails to complete the contract within the contract time specified in the contract documents, the Contractor will be charged liquidated damages for each working day that the Contractor fails to complete the construction project in accordance with the “schedule of liquidated damages” included in the project specifications. The RC/PM monitors the project progress and the Resident Engineer and Inspector documents any contract delays throughout the duration of the project. A Contractor request for a contract time extension shall be fully justified, adequately documented, and submitted at the time the excusable delay occurred. A revised progress schedule will be submitted documenting how this delay affected the critical path of the project work. Contract time extensions need approval from NJDOT and the Township of West Orange. Liquidated Damages Information regarding Liquidated Damages is included in the Contract Special Provisions – Time of Completion and Liquidated Damages are in agreement with 2019 NJDOT Standard Specification, Section 108.20, will be followed which is defined as the daily amount set forth in the contract to be deducted from the contract price to cover for additional cost incurred by the Township of West Orange because of the Contractor’s failure to complete work within the specified Contract Time. The Contractor must be advised by the Resident Engineer that Liquidated Damages will be assessed at each time that the progress schedule is not been met. LIQUIDATED DAMAGES or any other penalties proposed will be assessed from the original GRANT AMOUNT shown IN AGREEMENT. The Township of West Orange is solely responsible for producing any documents required by Federal Highway or NJDOT during the project lifecycle during and after the project is closed out throughout the record retention period. Progress Schedules The RC/PM with the assistance of the Resident Engineer reviews progress schedule and monitors the contract progress to evaluate impacts to contract time in accordance to Section 153 of NJDOT Standard Specifications. Progress payments are compensation for value of work performed during a covered period as specified in Title 23 CFR 635.123. The RC/PM monitors and